In February of 2025 MJM was awarded a project to replace an existing bottling line at Yuengling’s Tampa Plant. The project had an aggressive schedule and needed to be completed in a 4 week window. The work included remove of all existing filling equipment, labeler, CIP skids and associated conveyors. The installation included over 400 feet of conveyors, 40 motors and nearly 100 photo eye’s and proximity sensors. At the end of the 4 week schedule, Yuengling was creating a sellable product from the new line right on schedule.